WCMS Project Timeline

.

Major Milestones

Start

Finish

Phase 1 (Closed) October 2008 August 2009
Requirements preparation October 2008 October 2008
Requirements gathering October 2008 February 2009
Evaluate sites to migrate January 2009 March 2009
Create high-level implementation plan January 2009 March 2009
Evaluation and recommendation January 2009 August 2009
Present recommendation August 2009 August 2009
Phase 2 September 2009 October 2010
Purchase Cascade Server WCMS September 2009 November 2009
Implement Cascade Server WCMS November 2009 May 2010
Migrate Partner Sites May 2010 September 2010
Close Project (In Progress) September 2010 October 2010